LOCATION 47 - AUXILIARY OUTPUT 1, EVENT AND TIME (2 segments, numerical data)
Segment 1 Use the chart below to select the event that will activate auxiliary
output 1 (relay 1)
Segment 2 Program the timing from 0-255 (minutes or seconds, depending on the
data programmed in segment 1, location 46). Programming a “0”
makes the output follow the event
LOCATION 48 - AUXILIARY OUTPUT 2, EVENT AND TIME (2 segments, numerical data)
Segment 1 Use the chart below to select the event that will activate auxiliary
output 2 (relay 2)
Segment 2 Program the timing from 0-255 (minutes or seconds, depending on the
data programmed in segment 2, location 46). Programming a “0”
makes the output follow the event
LOCATION 49- AUXILIARY OUTPUT 3, EVENT AND TIME (2 segments, numerical data)
Segment 1 Use the chart below to select the event that will activate auxiliary
output 3
Segment 2 Program the timing from 0-255 (minutes or seconds, depending on the
data programmed in segment 3, location 46). Programming a “0”
makes the output follow the event
LOCATION 50- AUXILIARY OUTPUT 4, EVENT AND TIME (2 segments, numerical data)
Segment 1 Use the chart below to select the event that will activate auxiliary
output 4
Segment 2 Program the timing from 0-255 (minutes or seconds, depending on the
data programmed in segment 4, location 46). Programming a “0”
makes the output follow the event